Question 1

Ashley Mathias is the financial risk manager at Sycamore Bank. Ashley plans to design a contingency funding plan (CFP) for the institution. As a financial risk manager, which of the following considerations, will she not be mindful of when conducting this exercise? Ashley should ensure:

  1. Support by a communication plan
  2. Integration with broader risk management frameworks
  3. Inclusion of appropriate stakeholder groups
  4. No liquidity gap before beginning the exercise — Correct

Correct answer

No liquidity gap before beginning the exercise

Explanation

In designing a CFP, the onset of the exercise does not depend on whether there exists a liquidity gap or not. Liquidity gap analysis is a component of a CFP framework, hence a part of the whole exercise, but not a factor to consider before the exercise. A is incorrect: In designing a CFP, communication to clients, analysts, counterparties, and regulators with timely and accurate information is critical for enhancing confidence in the institution. B is incorrect: CFP should be integrated into other components of enterprise risk management (ERM) disciplines to increase its effectiveness and consistency. C is incorrect: Including the appropriate stakeholders when designing CFP is critical. Appropriate stakeholders provide a robust forum in which potential issues or challenges can be openly discussed and addressed. Such groups include the asset-liability committee (ALCO), risk and capital committee, investment committee, business units, finance, corporate treasury, risk, operations, and technology.

Question 2

The design of a CFP should integrate with the broader risk management frameworks. Which among the following choices is not part of the risk management frameworks under consideration?

  1. Enterprise risk management (ERM)
  2. Business continuity and crisis management
  3. Financial management — Correct
  4. Capital management

Correct answer

Financial management

Explanation

Financial management framework is not among the frameworks in a CFP design. However, it is an essential framework in the long-term council community plan (LTCP) analysis. A is incorrect: CFP is blended with enterprise risk management (ERM) components to enhance its effectiveness and consistency. B is incorrect: Integration of a CFP with the business continuity and crisis management is necessary as it reinforces significant operational and communication protocols in times of crisis. D is incorrect: The capital management framework is necessarily integrated with the CFP as it reinforces its effectiveness.

Question 3

Roy Jakes, the financial risk manager for Pathway Financial Institution, is preparing a design for a CFP. As an essential consideration in the plan, he must include appropriate stakeholders. Which among the following members is NOT part of the considered stakeholders?

  1. Internal audit committee — Correct
  2. Risk and capital committee
  3. Management committee
  4. Operations and technology

Correct answer

Internal audit committee

Explanation

Internal audit committee is not a stakeholder when designing a CFP. However, internal audit is involved with periodical reviews on the liquidity stress testing framework and procedures. B is incorrect: Risk and capital committee is an essential stakeholder responsible for setting the principles and parameters for measuring and assigning risk and capital within the business. C is incorrect: Different management committees such as the asset-liability committee (ALCO), risk and capital committee, and investment committee are key stakeholders in CFP. D is incorrect: The operational and technology committee reviews and approves the institution's technology planning and strategy.

Question 4

In JCL bank, Fatou James is the head of the corporate treasury. Which among the following choices best lists the roles of her committee?

  1. It serves as an advisor and counsel to the management committee and LCT teams.
  2. It monitors the ongoing business, funding risk, and liquidity profile as part of its BAU activities. — Correct
  3. It provides recommendations on CFP actions.
  4. It provides oversight of the LCT and does a consultation with the board of directors to monitor the institution's liquidity risk profile

Correct answer

It monitors the ongoing business, funding risk, and liquidity profile as part of its BAU activities.

Explanation

The corporate treasury monitors the ongoing business, funding, risk, and liquidity profile as part of its BAU activities. The treasury can consult the CFO and others to invoke the CFP and convene the liquidity crisis team (LCT) regarding a review of the markets, liquidity stress testing results, among others. A is incorrect: It is the role of the board of directors to advice and counsel the management committee and LCT teams. C is incorrect: It is the role of the liquidity crisis team (LCT) to provide recommendations on CFP actions. Moreover, the LCT designs the CFP, and submits it to the senior management for review and approval. D is incorrect: The management committee conducts the oversight of the LCT in consultation with the board of directors.

Question 5

An effective CFP should ensure that there are contingency plans in place to cushion the bank when certain events that can potentially impact liquidity happen. Which among the following events does NOT have a negative liquidity impact on a financial institution?

  1. Presence of predatory trade
  2. Unavailability of the Federal Home Loan Bank Funding
  3. Shifting allocation from short-term funding to long-term funding sources — Correct
  4. When the intraday debit cap with Fedwire is exceeded

Correct answer

Shifting allocation from short-term funding to long-term funding sources

Explanation

Shifting allocation from short-term funding to longterm funding sources is a contingent action/capital recovery action that strengthens the institution's liquidity position. A is incorrect: The presence of predatory trade causes liquidity dryness in the market, resulting in liquidity stress. B is incorrect: When Federal Home Loan Bank funding becomes unavailable, the financial institution under review may face liquidity stress. D is incorrect: When a financial institution exceeds its intraday cap, it implies that no more intraday liquidity can be issued, a situation that leads to liquidity stress.

Question 6

Several market factors can affect the institution's ability to take contingent actions that help in strengthening the institution's liquidity position. Which among the following factors does NOT pose such an effect to institutions?

  1. Shutdown of securitization markets
  2. Deposit runoff
  3. Failure of the counterparties to roll over their deposits
  4. Withdrawal of debit caps — Correct

Correct answer

Withdrawal of debit caps

Explanation

Withdrawing debit caps, though it may not be a typical scenario, does not have any effect on the institution's ability to take contingent actions. It just allows them to access more intraday credit. A is incorrect: Shutdown of securitization markets affects the institution's ability to take contingent actions as some of those actions rely on the security markets. B is incorrect: Deposit runoff affects the institution's ability to take contingent actions since some of the actions depend on the deposits. C is incorrect: Unwillingness of counterparties to roll over their deposits affects the institution's ability to take contingent actions.

Question 7

When designing a CFP, monitoring and escalation is a key component of the CFP framework. Institutions are required to define early warning indicators using market and business factors. Which of the following factors is NOT a potential factor considered?

  1. Macro-environment measures
  2. Industry measures
  3. Financial measures — Correct
  4. Institution-specific measures

Correct answer

Financial measures

Explanation

Institutions do not necessarily need information obtained from financial measures to define monitor trends in the market as well as among the institution's peer group. Moreover, a financial measure is a broad term. A is incorrect: Macro-environment factors may not directly correspond to individual liquidity challenges that an institution may face; however, they can provide insight into general market distress and a systemic withdrawal of liquidity, like the freezing of the repo markets during the financial crisis. B is incorrect: Industry measures gauge the profitability trend of the financial sector and the recent rating agency. Industry factors include trends in the profitability of the financial sector, recent rating agency action, banking industry capital adequacy, S&P financial institution sector movement, and other factors. Competitor analysis can also be applied to evaluate the trends in the industry to detect potential performance problems in an institution's peer group. D is incorrect: Institution-specific measures aid the management in assessing the market's perception of the institution's financial strength and the possibility of a liquidity crisis through external information. Internal measures provide greater insight into the operations of the institution and their potential impact on its liquidity position.

Question 8

Early warning indicators (EWIs) should act as warning signs to the management to evaluate how changing market conditions and the institution's business strategy may be impacted. This should prompt the management to act in advance of oncoming market disruptions proactively. Which among the following factors is NOT an EWI encompassing market and business factors?

  1. A spike in the market volatility
  2. An increase in asset quality — Correct
  3. Real or perceived negative publicity
  4. Canceling loan commitments and refusing to renew maturing loans

Correct answer

An increase in asset quality

Explanation

An increase in asset quality is not an EWI; however, a decrease in asset quality is. A is incorrect: A spike in market volatility is a warning sign of the onset of liquidity stress. C is incorrect: When there is negative publicity, whether real or perceived, especially about an institution's liquidity, a stress scenario may arise. D is incorrect: Canceling loan commitments and refusing to renew maturing loans indicate impending liquidity stress.

Question 9

An institution must monitor a suite of liquidity health ratios besides reviewing macro-economic and industry measures as part of a CFP framework. These ratios aid in quantifying the impact of liquidity risks and supporting decision making on the CFP actions under consideration. The used capacity to total borrowing capacity is one of the liquidity health ratios. Which of the following accurately describes this measure?

  1. Measures the borrowing capacity available to the institution, based on used capacity relative to the total borrowing capacity — Correct
  2. Measures the cushion that liquid assets offer over obligatory funding needs and can be used to track the level of liquid assets available to offset volatile funding
  3. Measures the exposure to credit facilities that may be required at a future date
  4. Measures the funding and borrowing enough to finance the institution's increased lending banking activities

Correct answer

Measures the borrowing capacity available to the institution, based on used capacity relative to the total borrowing capacity

Explanation

Used capacity to total borrowing capacity measures the borrowing capacity available to the institution, based on used capacity relative to the total borrowing capacity. B is incorrect: Liquid assets to volatile liabilities measure the primary surplus (cushion) that liquid assets offer over obligatory funding needs and can be used to track the level of liquid assets available to offset volatile funding. C is incorrect: Loans to commitments measures the exposure to credit facilities that may be required at a future date. As these commitments are drawn down, utilization increases, prompting a further need for funding to meet the obligations. D is incorrect: The description in D refers to the projected net funding requirements to current unused funding capacity measure. It provides an approach to assess the institution's future lending obligations in proportion to the total funds available at the institution.

Question 10

In designing a CFP, institutions develop a series of escalation levels adequately aligned to the scenarios, contingency actions, and liquidity measures. However, there are no guidelines in the number of escalation levels required by CFPs. Which among the following statements is correct about the first level of escalation?

  1. At this level, the institution focuses mainly on survival
  2. It represents the elevated monitoring of market conditions and its effect on the business performance — Correct
  3. At this level, the institution has experienced noticeable markets and idiosyncratic events that are adversely affecting its business and liquidity risk profile
  4. None of the above

Correct answer

It represents the elevated monitoring of market conditions and its effect on the business performance

Explanation

The first level of escalation represents the elevated monitoring of market conditions and their effect on the institution's business segments and performance. A is incorrect: The description in A refers to the final level of escalation. At the later stages of the crisis, the institution would have taken dramatic steps to stabilize its liquidity position, potentially including significant curtailing of liquidity intensive business activities or disposals/sales of businesses. C is incorrect: The description provided in C refers to the second level of escalation.