Question 1
In target costing, which of the following would be an appropriate strategy to reduce a cost gap for a product that existed in a competitive industry with demanding shareholders?
- Increase the selling price
- Reduce the expectation gap by reducing the selling price
- Reducing the desired margin on the product
- Mechanising production in order to reduce average production cost — Correct
Correct answer
Mechanising production in order to reduce average production cost
Explanation
Increasing the selling price is not possible; the industry is competitive so product will not sell effectively at higher prices. Reducing the expectation gap by reducing the selling price is not target costing. Reducing the desired margin on the product is not possible either: shareholders are demanding and would expect a good return. Mechanising production is a valid way to close a cost gap in target costing.
Question 2
Which of the following strategies would be an immediately acceptable method to reduce an identified cost gap?
- Reduce the desired margin without discussion with business owners
- Reduce the predicted selling price
- Source similar quality materials from another supplier at reduced cost — Correct
- Increase the predicted selling price
Correct answer
Source similar quality materials from another supplier at reduced cost
Explanation
To reduce the acceptable margin would normally require agreement from the owners and altering selling prices in any direction is not valid as the starting point of target costing is to find a competing product's price; this cannot be changed. Sourcing similar quality materials at lower cost is a common and immediate way to close a cost gap.
Question 3
The predicted selling price for a product has been set at 56 USD per unit. The desired mark-up on cost is 25% and the material cost for the product is estimated to be 16 USD before allowing for additional materials to allow for shrinkage of 20% (for every 10 kg of material going in only 8 kg comes out).
If labour is the only other cost and 2 hours are needed, what is the most the business can pay per hour if a cost gap is to be avoided?
The maximum rate per hour is (2 dp)
Correct answer
12.40
Explanation
Target cost = Selling price × (1 / (1 + mark-up)) = 56 × (1 / 1.25) = 44.80 USD. Material cost allowing for shrinkage = 16 × (10/8) = 20.00 USD. Labour cost allowable = 44.80 - 20.00 = 24.80 USD for 2 hours. Maximum rate per hour = 24.80 / 2 = 12.40 USD.
Question 4
Which of the following techniques is NOT relevant to target costing?
- Value analysis
- Variance analysis — Correct
- Functional analysis
- Activity analysis
Correct answer
Variance analysis
Explanation
Variance analysis is not relevant to target costing as it is a technique used for cost control at the production phase of the product life cycle. It is a feedback control tool by nature and target costing is feedforward. Value analysis can be used to identify where small cost reductions can be applied to close a cost gap once production commences. Functional analysis can be used at the product design stage. It ensures that a cost gap is reduced or eliminated by ensuring that the product design is one which includes only features which customers want. Activity analysis identifies and describes activities in an organisation and evaluates their impact on operations to assess where improvements can be made.
Question 5
The selling price of product Zeta is set to be 250 USD for each unit and sales for the coming year are expected to be 500 units. The company requires a return of 15% in the coming year on its investment of 250,000 USD in product Zeta.
What is the target cost for each unit of Zeta for the coming year?
- 145 USD
- 155 USD
- 165 USD
- 175 USD — Correct
Correct answer
175 USD
Explanation
Sales revenue 500 units @ 250 USD = 125,000 USD. Return on investment required 15% × 250,000 = 37,500 USD. Total cost allowed = 125,000 - 37,500 = 87,500 USD. Target cost per unit = 87,500 / 500 = 175 USD.
Question 6
An opticians firm provides a range of services to the public, such as eye tests and contact lens consultations, and has a separate dispensary selling glasses and contact lenses. Patients book appointments with an optician in advance.
A standard appointment is 30 minutes long, during which an optician will assess the patient's specific requirements and provide them with the eye care services they need. After the appointment, patients are offered the chance to buy contact lenses or glasses from the dispensary.
Which of the following describes a characteristic of the services provided by an optician at VC Co during a standard appointment?
- Tangible
- Homogeneous
- Non-perishable
- Simultaneous — Correct
Correct answer
Simultaneous
Explanation
It is simultaneous as there is no delay between the service being provided by the optician and consumed by the patient.
Question 7
Target costing is best described as:
- A technique to control costs after production has commenced
- A market-driven approach to establishing the maximum allowable cost for a product — Correct
- A method of absorbing overheads based on actual activity levels
- A process of setting selling prices based on full cost plus margin
Correct answer
A market-driven approach to establishing the maximum allowable cost for a product
Explanation
Target costing starts with a market-determined selling price and subtracts the desired profit margin to arrive at the target cost.
Question 8
Which of the following is a key feature of target costing?
- It is applied primarily during the production phase
- It focuses on achieving the lowest possible cost regardless of customer requirements
- It involves cross-functional teams working together from the design stage — Correct
- It uses historical costs as the basis for future pricing
Correct answer
It involves cross-functional teams working together from the design stage
Explanation
Target costing requires involvement from design, engineering, purchasing and production teams early in the product life cycle.
Question 9
A cost gap in target costing is the difference between:
- The current achievable cost and the target cost — Correct
- The selling price and the full production cost
- The budgeted cost and the actual cost
- The standard cost and the target cost
Correct answer
The current achievable cost and the target cost
Explanation
The cost gap is the excess of the estimated (or current) achievable cost over the target cost that must be closed through cost reduction efforts.
Question 10
Which TWO of the following are typical methods used to close a cost gap in target costing?
- Value engineering — Correct
- Increasing the desired profit margin
- Standard costing variance analysis
- Supplier negotiations for lower prices — Correct
Correct answer
Value engineering; Supplier negotiations for lower prices
Explanation
Value engineering redesigns the product to reduce costs while maintaining functionality. Negotiating with suppliers is common to lower component costs.