ACCA F5 - Performance Management · Section A

Standard Costing Practice Questions

Review 10 sample questions with their correct answers and explanations. Sign up free to continue with the full topic quiz.

Sign up free for the full quiz

Question 1

Which of the following best describes a 'basic standard' within the context of budgeting?

  1. A standard which is kept unchanged over a period of time — Correct
  2. A standard which is based on current price levels
  3. A standard set at an ideal level, which makes no allowance for normal losses, waste and machine downtime
  4. A standard which assumes an efficient level of operation, but which includes allowances for factors such as normal loss, waste and machine downtime

Correct answer

A standard which is kept unchanged over a period of time

Explanation

Basic standards are long-term standards that remain unchanged and are used as a benchmark for comparison over time.

Question 2

Which TWO of the following statements about budgets and standards are true?

  1. Budgets can be used in situations where output cannot be measured, but standards cannot be used in such situations — Correct
  2. Budgets can include allowances for inefficiencies in operations, but standards use performance targets which are attainable under the most favourable conditions
  3. Budgets are used for planning purposes, standards are used only for control purposes
  4. Standards which remain unaltered for long periods of time are referred to as basic standards — Correct

Correct answer

Budgets can be used in situations where output cannot be measured, but standards cannot be used in such situations; Standards which remain unaltered for long periods of time are referred to as basic standards

Explanation

Budgets can be monetary for non-output areas; standards require measurable output. Basic standards are unchanged over long periods.

Question 3

Which one of the following best defines standard costing in a system of budgeting?

  1. All activities are examined without reference to history each year
  2. Output level and costs are predetermined, actual results then compared with these predetermined costs and variances analysed — Correct
  3. Actual costs are compared with predetermined costs for the level of activity
  4. Costs are assigned to a manager in order that controllable and non-controllable costs are accounted for

Correct answer

Output level and costs are predetermined, actual results then compared with these predetermined costs and variances analysed

Explanation

Standard costing sets predetermined costs per unit for planning and control, with variance analysis.

Question 4

The following are management accounting techniques: (i) Actual versus flexed budget calculations. (ii) Variance analysis. (iii) Trend of costs analysis. Which of the above techniques could be used by a company to control costs?

  1. (i) and (ii) only
  2. (i) and (iii) only
  3. (ii) and (iii) only
  4. (i), (ii) and (iii) — Correct

Correct answer

(i), (ii) and (iii)

Explanation

All three are used for cost control: flexed budgets for volume adjustment, variances for detailed analysis, trends for long-term patterns.

Question 5

When considering setting standards for costing, which of the following would NOT be appropriate?

  1. The normal level of activity should always be used for absorbing overheads — Correct
  2. Average prices for materials should be used, encompassing any discounts that are regularly available
  3. The labour rate used will be the rate at which the labour is paid
  4. Average material usage should be established based on generally-accepted working practices

Correct answer

The normal level of activity should always be used for absorbing overheads

Explanation

Normal (long-run average) activity is used for overhead absorption to avoid volume variances from fluctuating activity.

Question 6

Which of the following statement(s) is/are true regarding standard costing and total quality management (TQM)? (1) They focus on assigning responsibility solely to senior managers. (2) They work well in rapidly changing environments.

  1. (1) only
  2. (2) only
  3. Neither (1) nor (2) — Correct
  4. Both (1) and (2)

Correct answer

Neither (1) nor (2)

Explanation

Standard costing is variance-focused and less compatible with TQM's continuous improvement and zero-defect philosophy. It works better in stable environments.

Question 7

A business is expanding rapidly and buying its material in a variety of countries in a variety of currencies. It has an exclusive supply delivery contract whereby the same logistics expert makes all deliveries in to its warehouses on a cost plus basis. It pays all delivery charges on a per unit basis. Which THREE of the following are valid explanations of an adverse material price variance measured to include delivery costs as part of the cost per kg delivered?

  1. Exchange rate movements — Correct
  2. Extra discounts agreed
  3. Increased world-wide demand for the material — Correct
  4. Extra supply of the material becoming available from new suppliers
  5. World oil price rises — Correct
  6. Increases in the dividends paid by the delivery business

Correct answer

Exchange rate movements; Increased world-wide demand for the material; World oil price rises

Explanation

Adverse price variance causes: exchange rate weakening, higher material demand pushing prices up, oil price rises increasing delivery costs.

Question 8

An ideal standard is best described as:

  1. A standard based on current levels of efficiency
  2. A standard which is unchanged over a long period
  3. A standard achievable under perfect operating conditions with no allowances for inefficiencies — Correct
  4. A standard reflecting efficient but attainable performance with normal allowances

Correct answer

A standard achievable under perfect operating conditions with no allowances for inefficiencies

Explanation

Ideal standards assume perfect conditions with no waste, losses or downtime.

Question 9

Attainable standards are most likely to:

  1. Demotivate employees
  2. Provide a realistic but challenging target — Correct
  3. Ignore normal inefficiencies
  4. Remain unchanged for many years

Correct answer

Provide a realistic but challenging target

Explanation

Attainable standards include normal allowances and motivate by being realistic.

Question 10

Current standards are:

  1. Updated regularly to reflect current conditions — Correct
  2. Set at perfect efficiency levels
  3. Unchanged over long periods
  4. Based solely on historical data

Correct answer

Updated regularly to reflect current conditions

Explanation

Current standards are revised frequently to reflect prevailing conditions.

Ready for the full quiz?

Create a free QuizAnalyst account to practice the complete question set and save your progress.

Sign up free for the full quiz