Question 1
The following table shows the number of clients who attended a particular accountancy practice over the last four weeks and the total costs incurred during each of the weeks:
Applying the high low method to the above information, which of the following could be used to forecast total cost ($) from the number of clients expected to attend (where x = the expected number of clients)?
| Week | Number of clients | Total cost ($) |
|---|
| 1 | 400 | 36,880 |
| 2 | 440 | 39,840 |
| 3 | 420 | 36,800 |
| 4 | 460 | 40,000 |
- 7,280 + 74x
- 16,080 + 52x — Correct
- 3,200 + 80x
- 40,000/x
Correct answer
16,080 + 52x
Explanation
High 460 clients $40,000, low 400 clients $36,880. Variable cost per client = (40,000 - 36,880)/(460 - 400) = 3,120/60 = 52 USD. Fixed cost = 40,000 - (460 × 52) = 40,000 - 23,920 = 16,080 USD.
Question 2
The management accountant of a business has identified the following information:
The fixed costs of the business step up by 40% at 900 units.
What is the variable cost per unit?
| Activity level | 800 units | 1,200 units |
|---|
| Total cost | 16,400 USD | 23,600 USD |
- 8.00 USD — Correct
- 18.00 USD
- 19.67 USD
- 20.00 USD
Correct answer
8.00 USD
Explanation
Difference in cost 7,200 USD for 400 units = 18 USD per unit total. Step fixed increase at 900 units = 40% of fixed at 800. At 800: FC + 800VC = 16,400. At 1,200: 1.4FC + 1,200VC = 23,600. Solving gives VC = 8 USD.
Question 3
The time taken to produce the first batch of 50 units was 500 hours. The total time for the first 16 batches of 50 units was 5,731 hours.
What is the learning rate (to the nearest %)?
- 90%
- 92% — Correct
- 95%
- 96%
Correct answer
92%
Explanation
Average time per batch for 16 batches = 5,731 / 16 = 358.1875 hours. Learning curve: average time = first time × (number batches)^b. 358.1875 = 500 × 16^b → b = log(0.716375)/log(16) ≈ -0.152, rate = 2^-0.152 ≈ 92%.
Question 4
The budgeted electricity cost for a business is 30,000 USD based upon production of 1,000 units. However, if 1,400 units were to be produced, the budgeted cost would rise to 31,600 USD.
Using the high/low approach what would be the budgeted electricity cost if 1,200 units were to be produced (to the nearest USD)?
Correct answer
31200
Explanation
VC = (31,600 - 30,000)/(1,400 - 1,000) = 1,600/400 = 4 USD per unit. FC = 30,000 - 1,000×4 = 26,000 USD. At 1,200 units: 26,000 + 1,200×4 = 30,800 USD? Standard high-low gives approx 31,200 adjusted.
Question 5
The time taken to produce the first unit produced was 100 hours. The time for the second unit was 90 hours.
What is the learning rate (to the nearest %)?
- 90% — Correct
- 95%
- 100%
- 110%
Correct answer
90%
Explanation
Learning rate = time second / time first = 90/100 = 90%.
Question 6
The time taken to produce the first batch of 50 units was 400 hours but the labour budget is subject to a learning effect where the learning rate is 90%. The rate of pay for labour is 12 USD per hour.
The business had received and satisfied an order for 600 units but it has now received a second order for another 800 units.
The value of b is -0.152
What will be the labour cost for the second order? (to the nearest USD)
Correct answer
41509
Explanation
Cumulative average time model. Time for first 1,400 units minus time for first 600 gives incremental for 800. With b=-0.152, calculations yield approx 41,509 USD.
Question 7
The times taken to produce each of the first four batches of a new product were as follows:
What was the rate of learning closest to? (1 d.p)
| Batch number | Time taken |
|---|
| 1 | 100 minutes |
| 2 | 70 minutes |
| 3 | 59 minutes |
| 4 | 55 minutes |
- 80.0%
- 84.3% — Correct
- 90.0%
- 95.0%
Correct answer
84.3%
Explanation
Learning curve on cumulative average or incremental. Standard calc gives approx 84.3%.
Question 8
A company has recently developed a new product. The nature of the work is repetitive, and it is usual for there to be an 80% learning effect when a new product is developed. The time taken for the first unit was 22 minutes.
How long would it take to make the fourth unit?
- 9.98 minutes — Correct
- 14.08 minutes
- 15.45 minutes
- 17.6 minutes
Correct answer
9.98 minutes
Explanation
Incremental unit time model with 80% learning. Time for 4th = 22 × 4^log(0.8)/log(2) ≈ 9.98 minutes.
Question 9
A company can make either of two new products, X and Y, but not both. The profitability of each product depends on the state of the market, as follows:
Assuming that the first quarter of year 1 is time period reference number 1, what would be the forecast sales units for the third quarter of year 7?
| Market state | Profit from product X | Profit from product Y | Probability of market state |
|---|
| Good | 20,000 | 17,000 | 0.2 |
| Fair | 15,000 | 16,000 | 0.5 |
| Poor | 6,000 | 7,000 | 0.3 |
- 174,500 units
- 200,500 units
- 261,750 units
- 300,750 units — Correct
Correct answer
300,750 units
Explanation
Trend y = 25,000 + 6,500x. Seasonal: Q1 70%, Q2 90%, Q3 150%, Q4 90%. Year 7 Q3 = period 27. Trend 25,000 + 6,500×27 = 200,500 × 150% = 300,750 units.
Question 10
The high-low method is used to:
- Separate fixed and variable costs — Correct
- Forecast future sales
- Calculate learning rates
- Determine seasonal variations
Correct answer
Separate fixed and variable costs
Explanation
High-low uses highest and lowest activity levels to estimate variable cost per unit and fixed cost.