Question 1
When establishing standards for a costing system, which of the following would NOT be an appropriate principle?
- The normal level of activity should always be used for absorbing overheads — Correct
- Average prices for materials should be used, encompassing any discounts that are regularly available
- The labour rate used will be the rate at which labour is paid
- Average material usage should be established based on generally-accepted working practices
Correct answer
The normal level of activity should always be used for absorbing overheads
Explanation
Overhead absorption should be based on normal or expected activity, not necessarily the actual normal level.
Question 2
What are performance standards that have remained unchanged over a long period of time known as?
- Ideal standards
- Current standards
- Basic standards — Correct
- Attainable standards
Correct answer
Basic standards
Explanation
Basic standards are historical standards left unchanged for comparison over time.
Question 3
What are performance standards that allow for efficient but not perfect operating conditions known as?
- Ideal standards
- Current standards
- Basic standards
- Attainable standards — Correct
Correct answer
Attainable standards
Explanation
Attainable standards are practical targets allowing for normal losses and inefficiencies.
Question 4
Which of the following statements are true and which are false?
- A variance is the difference between budgeted and actual cost. — False
- A favourable variance means actual costs are less than budgeted. — True
- An adverse variance means that actual income is less than budgeted. — True
- A variance is the difference between the flexed budget cost and the actual cost. — False
Correct answer
A variance is the difference between budgeted and actual cost. — False
A favourable variance means actual costs are less than budgeted. — True
An adverse variance means that actual income is less than budgeted. — True
A variance is the difference between the flexed budget cost and the actual cost. — False
Explanation
Variances compare flexed (not original) budget to actual. Favourable means better than expected (lower cost or higher revenue).
Question 5
Ideal standards are those that can be attained:
- Under perfect operating conditions with no inefficiencies — Correct
- Under normal operating conditions with allowances for losses
- Based on current performance levels
- Using historical data unchanged over time
Correct answer
Under perfect operating conditions with no inefficiencies
Explanation
Ideal standards assume 100% efficiency and no waste.
Question 6
Current standards are based on:
- The expected performance in the current period — Correct
- Perfect efficiency
- Long-term unchanged levels
- Attainable targets with motivation in mind
Correct answer
The expected performance in the current period
Explanation
Current standards reflect present conditions and are updated regularly.
Question 7
Which type of standard is most likely to motivate employees?
- Attainable standards — Correct
- Ideal standards
- Basic standards
- Current standards
Correct answer
Attainable standards
Explanation
Attainable standards are challenging but achievable, promoting motivation.
Question 8
Basic standards are most useful for:
- Trend analysis over long periods — Correct
- Short-term performance evaluation
- Motivating operational staff
- Calculating current variances
Correct answer
Trend analysis over long periods
Explanation
Unchanged basic standards allow comparison of efficiency over time.
Question 9
When setting a standard material price, which factor should be considered?
- Expected purchase price including reliable discounts — Correct
- Historical average price without adjustment
- Ideal price assuming perfect market conditions
- Current spot price only
Correct answer
Expected purchase price including reliable discounts
Explanation
Standards use expected realistic prices with normal discounts.
Question 10
Ideal standards may lead to:
- Demotivation due to unattainability — Correct
- Accurate short-term control
- Reduced variance investigation
- Better long-term planning
Correct answer
Demotivation due to unattainability
Explanation
Ideal standards are rarely achieved, causing frustration.