Question 1

Which of the following best describes a flexible budget?

  1. A budget for semi-variable overhead costs only
  2. A budget which, by recognising different cost behaviour patterns, is designed to change as volume of activity changes — Correct
  3. A budget for a twelve month period which includes planned revenues, expenses, assets and liabilities
  4. A budget prepared for a rolling period which is reviewed monthly, and updated accordingly

Correct answer

A budget which, by recognising different cost behaviour patterns, is designed to change as volume of activity changes

Explanation

A flexible budget adjusts for changes in activity level by recognising different cost behaviour patterns.

Question 2

What is a primary purpose of using a flexible budget?

  1. To cap discretionary expenditure
  2. To produce a revised forecast by changing the original budget when actual costs are known
  3. To identify revenues and costs at different budgeted activity levels — Correct
  4. To communicate target activity levels within an organisation by setting a budget in advance of the period to which it relates

Correct answer

To identify revenues and costs at different budgeted activity levels

Explanation

Flexible budgets allow comparison of costs and revenues at varying activity levels for better control.

Question 3

Which of the following best describes a fixed budget?

  1. A budget for a single level of activity — Correct
  2. A budget used when the mix of products is fixed in advance of the budget period
  3. A budget which ignores inflation
  4. An overhead cost budget

Correct answer

A budget for a single level of activity

Explanation

A fixed budget is prepared for one planned activity level and does not adjust for actual volume.

Question 4

Which of the following statements are correct? (i) A fixed budget is a budget that considers all of an organisation's costs and revenues for a single level of activity. (ii) A flexible budget is a budget that is produced during the budget period to recognise the effects of any changes in prices and methods of operation that have occurred. (iii) Organisations can use budgets to communicate objectives to their managers.

  1. (i) and (ii) only
  2. (i) and (iii) only — Correct
  3. (ii) and (iii) only
  4. All of them

Correct answer

(i) and (iii) only

Explanation

(i) and (iii) are correct. (ii) is incorrect as flexible budgets adjust for volume changes, not price or method changes during the period.

Question 5

Horizon Press produces and sells textbooks for schools and colleges. The following budgeted information is available for the year ending 31 December 20X6. What does the flexed budget show?

BudgetFlexed BudgetActual
Sales (units)120,000100,000100,000
Sales revenue50005000995
Variable printing costs1,2001,000280
Variable production overheads36030056
Fixed production cost300300364
Fixed administration cost360360364
Profit/(Loss)120(10)5
  1. a profit of 10,000
  2. a loss of 10,000 — Correct
  3. a profit of 100,000
  4. a loss of 100,000

Correct answer

a loss of 10,000

Explanation

Flexed at 100,000 units shows a loss of 10.

Question 6

Which of the following statements is true?

  1. A fixed budget is a budget that remains the same from one accounting period to the next
  2. A fixed budget is produced for one product for different levels of activity
  3. A flexible budget is designed to change as activity levels change — Correct
  4. A fixed budget is useful when comparing budget figures with actual figures

Correct answer

A flexible budget is designed to change as activity levels change

Explanation

Flexible budgets adjust with changes in activity level, while fixed budgets do not.

Question 7

The following budgeted information comes from the accounting records of Taylor. In a period where the actual sales were 1,200 units, what would be the budgeted flexed profit?

Original BudgetFlexed Budget
Sales units1,0001,200
Sales revenue100,000120,000
Direct material40,00048,000
Direct labour20,00024,000
Variable overhead15,00018,000
Fixed overhead10,00010,000
Profit15,00020,000
  1. 17,000
  2. 20,000 — Correct
  3. 22,000
  4. 35,000

Correct answer

20,000

Explanation

Flexed profit at 1,200 units is 20,000.

Question 8

When budgeting, what are variable costs conventionally deemed to do?

  1. Be constant per unit of output — Correct
  2. Vary per unit of output as production volume changes
  3. Be constant in total when production volume changes
  4. Vary in total, from period to period when production is constant

Correct answer

Be constant per unit of output

Explanation

Variable costs are constant per unit but vary in total with activity.

Question 9

MNO Ltd makes a single product for which the budgeted costs and activity for a typical month are as follows: Budgeted production and sales 15,000 units Budgeted unit costs: Direct materials 30 Direct labour 46 Variable overheads 24 Fixed overheads 80 The standard selling price of the product is 220 per unit. During October only 13,600 units were produced. What is the total budget cost allowance contained in the flexed budget for October?

  1. 1,800,000
  2. 2,200,000
  3. 2,560,000 — Correct
  4. 2,700,000

Correct answer

2,560,000

Explanation

Variable per unit 100. Flexed variable 13,600 × 100 = 1,360,000. Fixed 1,200,000. Total 2,560,000.

Question 10

The following extract is taken from the overhead budget of PQR Ltd: Budgeted activity 50% 75% Budgeted overhead 100,000 112,500 What would the budgeted overhead cost be for an activity level of 80%?

  1. 115,000 — Correct
  2. 120,000
  3. 160,000
  4. 360,000

Correct answer

115,000

Explanation

Variable per 25% increase 12,500 / 25 = 500 per %. Fixed 100,000 - (50 × 500) = 75,000. At 80% 75,000 + 80 × 500 = 115,000.

Ready for the full quiz?