Question 1
Which TWO of the following approaches are most likely to be effective in achieving cost control?
Place a tick in the appropriate column for each item.
- Establishing performance targets for cost centre managers — Yes
- Lowering the budgeted cost level — No
- Performing cost variance analysis — Yes
- Expanding sales volume — No
Correct answer
Establishing performance targets for cost centre managers — Yes
Lowering the budgeted cost level — No
Performing cost variance analysis — Yes
Expanding sales volume — No
Explanation
Setting targets for cost centre managers and cost variance analysis are direct methods of monitoring and controlling costs. Simply lowering the budget does not control costs, and increasing sales volume would typically lead to an increase in costs.
Question 2
Value analysis primarily aims to achieve which of the following objectives?
Place a tick in the appropriate column for each item.
- Control costs — No
- Reduce costs — Yes
- Improve sales — No
- Increase the value of the product — Yes
Correct answer
Control costs — No
Reduce costs — Yes
Improve sales — No
Increase the value of the product — Yes
Explanation
Value analysis looks at costs not sales. The value of the product should not change if value analysis is applied correctly, but costs are reduced.
Question 3
Which of the following definitions best describes work study?
- The systematic examination of activities to improve resource utilisation — Correct
- The measurement of actual work against a predetermined standard
- The evaluation of job roles within an organisation
- The analysis of methods to establish time standards for tasks
Correct answer
The systematic examination of activities to improve resource utilisation
Explanation
Work study is defined as the systematic examination of work methods and the equipment used in performing a job, the design of an optimum work method and the standardisation of proposed work methods.
Question 4
Indicate whether each of the following activities relates to value analysis or value engineering.
- Examining existing products to identify cost reduction opportunities — Value analysis
- Reviewing product designs prior to production to minimise costs — Value engineering
Correct answer
Examining existing products to identify cost reduction opportunities — Value analysis
Reviewing product designs prior to production to minimise costs — Value engineering
Explanation
Value analysis reviews current products to reduce costs. Value engineering reviews products at the design stage to reduce costs.
Question 5
Which of the following techniques are useful for monitoring and controlling costs?
(i) Actual versus flexed budget comparison
(ii) Variance analysis
(iii) Trend of costs analysis
- (i) and (ii) only
- (i) and (iii) only
- (ii) and (iii) only
- (i), (ii) and (iii) — Correct
Correct answer
(i), (ii) and (iii)
Explanation
All the techniques listed in the question could be used to monitor and control costs.
Question 6
Value analysis is primarily concerned with
- Increasing the functionality of a product while maintaining costs
- Reducing the cost of a product without reducing its perceived value — Correct
- Improving the quality of materials used in production
- Expanding the range of features offered to customers
Correct answer
Reducing the cost of a product without reducing its perceived value
Explanation
Value analysis aims to reduce costs while maintaining the value or functionality of the product from the customer's perspective.
Question 7
Which of the following is a key difference between value analysis and value engineering?
- Value analysis is applied to existing products; value engineering is applied at the design stage — Correct
- Value analysis focuses on functionality; value engineering focuses on cost
- Value analysis is used in service industries; value engineering in manufacturing
- Value analysis requires customer input; value engineering does not
Correct answer
Value analysis is applied to existing products; value engineering is applied at the design stage
Explanation
Value analysis reviews costs on products already in production, whereas value engineering applies the same principles at the design or planning stage before production begins.
Question 8
An organisation is reviewing its procurement process to achieve cost reduction. Which of the following actions is most consistent with value analysis principles?
A Negotiating longer payment terms with suppliers
B Eliminating unnecessary functions from a component without affecting performance
C Increasing inventory levels to obtain bulk discounts
D Outsourcing non-core activities to specialist providers
- Negotiating longer payment terms with suppliers
- Eliminating unnecessary functions from a component without affecting performance — Correct
- Increasing inventory levels to obtain bulk discounts
- Outsourcing non-core activities to specialist providers
Correct answer
Eliminating unnecessary functions from a component without affecting performance
Explanation
Value analysis seeks to eliminate unnecessary costs by removing functions that do not add value while preserving the product's essential performance.
Question 9
Which TWO of the following are typical techniques used in value engineering?
- Functional analysis — Correct
- Target costing
- Life cycle costing — Correct
- Variance analysis
Correct answer
Functional analysis; Life cycle costing
Explanation
Value engineering commonly involves functional analysis to identify necessary functions and life cycle costing to consider costs over the product's entire life.
Question 10
A company applies value analysis to an existing product and identifies that a particular component can be replaced with a cheaper alternative that performs the same function.
This is an example of achieving cost reduction through
- Elimination
- Simplification
- Standardisation
- Substitution — Correct
Correct answer
Substitution
Explanation
Substitution involves replacing a component or material with a less expensive alternative that provides the same function.