Which document records the hours worked by an employee during a period?
Correct answer
Clock card
Explanation
Clock cards or time sheets record the actual hours worked by employees.
ACCA F2 - Management Accounting · Section A
Review 10 sample questions with their correct answers and explanations. Sign up free to continue with the full topic quiz.
Sign up free for the full quizWhich document records the hours worked by an employee during a period?
Clock card
Clock cards or time sheets record the actual hours worked by employees.
Which item is classified as direct labour?
Operator assembling products
Direct labour refers to workers directly involved in manufacturing the product.
Which item is treated as indirect labour?
Supervisor overseeing workers
Supervisors do not work directly on units produced and therefore are indirect labour.
Which statements regarding time rate payment are correct?
Statement Payment is based on hours worked. Time rate encourages high output. Time rate requires supervision to maintain productivity.
Statements 1 and 3
Time rate pays workers for time spent; close supervision may be required.
Which payment method rewards employees for the number of units they complete?
Piecework system
Piecework payment is based on output achieved.
A worker is paid a basic rate of 12 per hour and overtime at time and a half. What is the overtime rate?
15
Time and a half equals basic rate multiplied by 1.5.
A company is considering introducing a bonus scheme. Which factor indicates a risk of poor quality output?
Paying bonuses for exceeding time targets
Linking pay to speed may encourage rushed work and lower quality.
Which document authorises overtime work?
Overtime authorisation slip
Formal approval is required before overtime is undertaken.
A firm records labour cost variances monthly. Which two variances measure labour efficiency and labour rate performance?
Labour efficiency variance; Labour rate variance
Labour efficiency relates to hours worked versus standard; rate variance compares actual and standard wage rates.
Which of the following is a possible cause of labour idle time?
Machine breakdown
Breakdowns or delays cause workers to be paid for time not worked.